Glossary entry

Spanish term or phrase:

Subestación de Conexión y Medida

English translation:

Connection and metering substation

Added to glossary by Abril Wagner
Apr 21, 2019 19:27
5 yrs ago
6 viewers *
Spanish term

Subestación de Conexión y Medida

Spanish to English Tech/Engineering Electronics / Elect Eng Centrales de generación
¡Hola!

Nuevamente les solicito su ayuda. Se trata de la descripción de un proyecto de energía solar. Dice así:

La conexión del parque se realiza a través de 2 subestaciones: una subestación de transformación (150kV/31,5kV); y una subestación de Conexión y Medida con una Línea de Alta Tensión de 150 kV y 7km, la cual conecta a la subestación Salto Grande Uruguay (SGU).

Mi intento:

The connection of the power station is achieved through two substations: a 150kV/31.5kV substation and a connection and measurement station with a 150kV high voltage line spanning 7 km and connecting this station with Salto Grande Uruguay (SGU) substation.

Como nunca vi el término "subestación de Conexión y Medida", creo que se trata más bien de un puesto, por eso lo cambié. Agradeceré cualquier crítica y comentarios.
Proposed translations (English)
4 +1 connection and meter substation

Discussion

Helena Chavarria Jul 24, 2020:
@Abril Thank you for the information.
Abril Wagner (asker) Jul 24, 2020:
UTILITY SUBSTATION So much time later, I got the thruth on this term directly form the horse's mouth: the subestación o puesto de conexión y medida is a substation with all equipment except for a transformer, and that is built justo because the utility demands it from the private owner of a plant, for ex. It's like a burocracy requirement, so here the client calls it "utility substation".

Proposed translations

+1
4 hrs
Selected

connection and meter substation

Beginning of construction works
Execution of works for the connection substation (Cerro Colorado Station) begins.
http://www.astidey.com.uy/en/news/beginning-of-construction-...

The following figure shows the wind turbines' layout, the 30kV network, the internal roads, the internal substation and UTE's connection substation.
http://www.astidey.com.uy/en/content/wind-farm

EN
Meter substation
LENGUA DE DESTINO
Subestación de medición
https://www.era.europa.eu/sites/default/files/activities/doc...
Peer comment(s):

agree neilmac : Or "metering"...
8 hrs
De acuerdo, también "metering". Muchas gracias, Neil.
Something went wrong...
4 KudoZ points awarded for this answer. Comment: "Thank you, Wilsonn!"

Reference comments

43 mins
Reference:

Refs.

https://www.osha.gov/SLTC/etools/electric_power/illustrated_...




https://www.iic.org/en/projects/project-disclosure/11624-02/...
The project consists of the installation of 35 Vestas V110-2.0 wind turbines with nominal capacity of 2.0 MW each, for a total installed capacity of 70 MW. The wind farm will be built under an operating lease agreement with the UTE. The project has a significant positive environmental impact given that it will generate electricity from a renewable resource and will result in a reduction in greenhouse gas emissions. The project includes the construction of a measuring and cutting station, a control center, a transformer substation, and a 150 kV transmission line of 6 km to connect the wind farm to the existing Salto-Arapey line. Also, 20 km of internal roads will be built, 7 m wide, to enable access to each of the wind turbines, to the substation, and to the control and measurement stations. The wind turbines will be connected to the substation with medium-voltage (31.5 kV) underground cables.


How are CTs connected in the 33/11 KV substation? - Quora
https://www.quora.com/How-are-CTs-connected-in-the-33-11-KV.... -
31 ago. 2018 - They are used in a substation for metering and protection purpose. CT primary winding is connected in series with line while the secondary ... (this is where I got the idea of "metering").


http://biblioteca.olade.org/opac-tmpl/Documentos/hm000176.pd...
see pages 15 onwards about "Salto Grande" in English. I doubt it will help much.


https://www.saltogrande.org/transmision.php



What I would say is a "connecting and metering substation".
Peer comments on this reference comment:

agree JohnMcDove : As an answer?
1 hr
Thanks John, but I am still not 100% confident about "connecting".
agree neilmac : A "connection and metering substation" is what I was going to post, but Wilson got there first...
12 hrs
Thanks Neil.
agree Helena Chavarria : I thought I agreed with your references yesterday, but I must have dreamt it!
18 hrs
Thank you Helena. Happy Easter!
Something went wrong...
1 hr
Reference:

In general this circuit breaker is located at the medium voltage system inside a substation, where also the electricity meter for the settlement purposes is installed. This usually has its own voltage and current transformers.

-------------------------------------------------------
The main components for the grid connection of the WT are the transformer and the substation with the circuit breaker and the electricity meter inside it. Because of the high losses in low voltage lines, each Figure 1.1: Yearly installed capacity of wind energy in Europe and wold-wide of the turbines has its own transformer from the voltage level of the WT (400 or 690 V) to the medium voltage line. The transformer are located directly beside the WT to avoid long low-voltage cables. Only for small WTGS it is possible to connect them directly to the low voltage line of the grid without a transformer or, in a wind farm of small WT, to connect some of the small WT to one transformer. For large wind farms a separate substation for transformation from the medium voltage system to the high voltage system is necessary.

https://ec.europa.eu/energy/sites/ener/files/documents/2001_...
Peer comments on this reference comment:

agree JohnMcDove
39 mins
Thank you, John :-)
Something went wrong...
Term search
  • All of ProZ.com
  • Term search
  • Jobs